Date Issued
|
Report Number
17-05859-131
No. 1
to Office of Management (OM)
Closure Date: 3/10/2020
The Principal Executive Director and Chief Acquisition Officer for the Office of Acquisition, Logistics, and Construction ensure there are adequate funds available to routinely conduct planning activities, including developing requests for lease proposals, for Strategic Capital Investment Planning approved major leases while waiting for congressional authorization.
No. 2
to Office of Management (OM)
Closure Date: 1/15/2020
The Assistant Secretary for Management and Chief Financial Officer reconsider centralizing major medical lease acquisition funding through VA’s acceptance of the completed building.
No. 3
to Office of Management (OM)
Closure Date: 3/10/2020
The Principal Executive Director and Chief Acquisition Officer for the Office of Acquisition, Logistics, and Construction obtain adequate resources to deliver leases on schedule.
No. 4
to Office of Management (OM)
Closure Date: 1/15/2020
The Assistant Secretary for Management ensure that the prospectus cost estimates provided to Congress are accurate and the costs are allocated appropriately to comply with OMB Circular A-11 requirements.
No. 5
to Office of Management (OM)
Closure Date: 1/15/2020
The Principal Executive Director and Chief Acquisition Officer for the Office of Acquisition, Logistics, and Construction implement a comprehensive VA policy for critical decisions in the lease acquisition process establishing clear lines of authority and allowable time frames.
No. 6
to Acquisitions, Logistics, and Construction (OALC)
Closure Date: 8/24/2021
The Deputy Under Secretary for Health for Operations and Management and the Executive Director, Office of Construction Facilities Management, ensure VA uses appropriate security measure requirements when acquiring VA major medical leases by performing Interagency Security Committee risk evaluations prior to solicitation.
No. 7
to Office of Management (OM)
Closure Date: 3/10/2020
The Executive Director, Office of Construction Facilities Management, ensure project acquisition teams are adequately trained in performance-based acquisition.
No. 8
to Office of Management (OM)
Closure Date: 3/10/2020
The Executive Director, Office of Construction Facilities Management, evaluate the use of consultants in the solicitation development process for Requests for Lease Proposals of major medical leases on a case-by-case basis.
Total Monetary Impact of All Recommendations
Open: $ 0.00
Closed: $ 152,300,000.00